A
Brief History of the
Crawford School
Renovation Progress
March 2005 -
Restoration work on first floor
begins in
preparation for "The Music Man" in July
2005.
November 2004 -
Exterior masonry complete. Front entrance excavated
and restored to original configuration. Watch
the front entrance reappear...
July 2004 - Work
to begins on exterior masonry. Interior work
will begin in February 2005
November 2003
- Bidding process begun for the first phase of
renovations. Interior and exterior masonry are
tops on our list.
October 2003 - First
window adopted! Many thanks to John and
Linda Blanchard who are the proud sponsors of an
auditorium window.
September 2003
- A!O Truck Raffle Raises $13,00 for Schoolhouse Fund.
Billy Bryant was the proud winner...
|